Vung Ang 1 Thermal Power Plant – Combustion Tuning Test

Combustion Tuning Test

  • Chugai Technos, having gained the trust of the contractor Babcock & Wilcox Vietnam, successfully conducted the combustion tuning test for the boiler and auxiliary systems following the overhaul of the Unit 2, with bellow items:
    • Air balance test.
    • Adjustment of primary air (PA), secondary air (SA) and dirty air (DA).
    • Coal fineness check.
    • Combustion tuning check.
  • Scope of Works:
    • Measurement of primary air (PA), secondary air (SA) and dirty air (DA) flow rates.
    • Measurement of air flow at coal injection pipes.
    • Continuous monitoring of temperature, NOx-CO-CO2-O2 concentrations at the outlet of the economizer.
    • Monitoring and analysis of exhaust gas quality at the outlet of the economizer.
    • Sampling and analysis of coal injected into the boiler.
    • Sampling and analysis of fly ash quality.
  • Use of a simple and easily assembled equipment system to meet the specific requirements of the sampling location (horizontal pipes, off-floor sampling holes, limited space).
  • Parameters for monitoring and analysis:
    • Exhaust gas: temperature, pressure, velocity, flow rate, moisture content, gas composition (O2, CO2, and N2), dust concentration; NOx-SO2-CO-CO2-O2 concentration;
    • Fine coal: particle size, unburned carbon (UBC).
  • Report contents:
    • Basic exhaust gas parameters (including temperature, pressure, velocity, flow rate, moisture content, gas composition).
    • NOx-SO2-CO-CO2-O2 concentration;
    • Dust concentration;
    • Distribution of temperature, velocity, dust concentration; NOx-CO-CO2-O2 concentration;
    • Analysis result of coal and fly ash.
  • Chugai Technos engineering team carried out the work under challenging nighttime operational conditions at the Vung Ang 1 Thermal Power Plant, in close coordination with the operations unit. Accurate and timely data provision was ensured. Leveraging the expertise of experienced engineers and industry-leading specialists from Japan, Chugai Technos worked collaboratively with the customer to develop the optimal plan, meeting real-world conditions and supporting the boiler manufacturer in operating the system under the best possible conditions.

Some pictures during the implementation of the project:

Measurement of primary air (PA), secondary air (SA) flow rates

 NOx-O2 continuous monitoring

NOx-O2 sampling tubes

Discussion of measurement results

Coal sampling at injection pipes