Nghi Son 2 Thermal Power Plant

Electrostatic Precipitator (ESP) Performance Test :

  • Receiving the trust of MHPS-ES Contractor, Chugai Technos performed the performance testing of the ESP system for 2 units during the plant acceptance test.
  • Using simple equipment system, easy to assemble, suitable for ESP horizontal ducts. Sampling and monitoring equipment complies with Japanese JIS standards.
  • Monitoring parameters: Temperature, pressure, velovity, flow rate, moisture content, gas composition (O2, CO2 and N2), dust concentration.
  • Report contents:
    • The basic exhaust gas parameters;
    • Dust concentration;
    • Dust collection efficiency;
    • Distribution diagram: flow velocity, temperature, dust concentration;
    • Comparison of actual measurement results and DCS data;
    • Data analysis, general evaluation and giving improvement plan;

Some pictures during the implementation of the project:

Preparation work

Sampling equipment system

Monitoring of temperature and pressure of exhaust gas

Monitoring of moisture content

Determination of gas composition

Monitoring of dust concentration